Solar energy · Middle East
SASO and SABER: Getting Solar Equipment Into Saudi Arabia
Solar modules and inverters need conformity certificates before they clear Saudi customs. How SALEEM, SABER, PCoC and SCoC fit together, and where exporters get caught.

A solar consignment held at a Saudi port is an expensive way to learn about conformity assessment. It is also a common one, because the requirement is easy to discover late: the paperwork that matters is not the sales contract, it is the certificate the customs system expects to find.
This article sets out how the Saudi conformity regime is structured for solar equipment. It is a map, not a substitute for the current requirements published by SASO and your conformity assessment body — those change, and they are the authority.
The three names you will encounter
SALEEM is the Saudi Product Safety Program, the national framework under which imported and locally produced goods are assessed against applicable technical regulations.
SABER is the electronic platform through which that assessment is transacted. Suppliers and importers register products and shipments there and obtain certificates through it.
SASO — the Saudi Standards, Metrology and Quality Organization — is the body that sets the technical regulations and standards the products are assessed against.
In practice, an exporter deals with SABER as a system and with an approved conformity assessment body as the organisation that actually reviews evidence and issues certificates.
Two certificates, two jobs
This is where most confusion sits, and the distinction is worth learning properly because the costs of getting it wrong are logistical.
Product Certificate of Conformity (PCoC) attaches to a product model. It confirms that the model meets the applicable requirements, and it is typically issued with a one-year validity. That makes it a recurring obligation: a model you shipped last year is not automatically covered this year, and a supplier with a broad catalogue is managing a renewal calendar rather than a single approval.
Shipment Certificate of Conformity (SCoC) attaches to a consignment. It is issued per shipment and is what customs requires in order to release the goods.
The sequence matters. The shipment certificate generally depends on the product certificate already being in place, so a company that starts the process when the container is already at sea has left it too late.
What the technical regulations cover
SASO has implemented technical regulations addressing small-scale solar photovoltaic systems. The scope reaches solar panels, inverters, assembly and combiner boxes and related system components, and Argaam reported the implementation when it began.
The requirements span the areas you would expect for equipment carrying DC at voltage on a roof in high ambient temperature:
- Electrical safety of components and assemblies.
- Fire safety, including firefighting considerations for PV systems.
- Electromagnetic compatibility.
- Protection requirements for system components.
Component-level standards apply beneath these. PV DC surge protection, for instance, is assessed against IEC 61643-31. Your conformity assessment body will identify the applicable standard list for your specific product; it is not something to infer from a general regulation title.
Where existing test reports help — and where they do not
Photovoltaic products have been brought within SASO's IECEE recognition arrangements, which means testing already performed under that international scheme may be usable rather than repeated. For a manufacturer with a mature certification file, that can remove significant cost and time.
It is not a free pass. Recognition arrangements have a defined scope, they are revised, and what was accepted in a previous cycle may not map onto the current requirement. UL Solutions has tracked changes to the recognition arrangement, which is a reasonable indicator of how often this moves.
The practical instruction is simple: ask which of your existing reports are usable before you budget for the project, not after. The answer determines whether you are looking at a documentation exercise or a re-testing programme.
Three things that are not the same
Suppliers routinely conflate these, and each is a separate gate:
- Conformity assessment establishes that your product may be sold and imported. It is SASO's domain.
- Supplier registration and qualification establishes that your company may transact with a given buyer. That is the buyer's domain, and we map it in qualifying as a renewable energy supplier in Saudi Arabia.
- Grid connection approval establishes that a specific piece of equipment may be connected to the network. That is the network operator's domain.
An inverter can clear customs and still not be approvable for connection. A company can be a registered supplier and still have uncertified product. Track all three.
The environmental specification is not a formality
There is a technical dimension here that catches suppliers whose products were designed for temperate markets, and it interacts with compliance rather than sitting apart from it.
Gulf operating conditions are severe and sustained: high ambient temperature, intense irradiance, dust loading and soiling. These affect the ratings a product must actually hold up to, and therefore the evidence behind the certification. We cover the underlying physics in solar panels in extreme heat and dust and soiling on solar panels.
Buyers in the region are well aware of the difference between a datasheet figure and field behaviour in a Saudi summer. Certification gets you into the market; performance in these conditions is what keeps you there.
A sequence that works
For a manufacturer approaching the market for the first time:
- Identify the applicable technical regulation and standard list for your specific products.
- Establish which existing test evidence is recognised and what must be generated.
- Obtain the product certificates, allowing for the renewal cycle.
- Register your company with the buyers you actually intend to sell to.
- Confirm network-side requirements separately if the equipment connects to a grid.
- Only then commit to shipping schedules.
Compressing that sequence is where the port-side costs come from.
Sell into the Gulf with the requirements in view
Arcnex covers the compliance and procurement machinery around Gulf renewable projects, not just the announcements — free, with no paywall between you and a working answer.
- Follow our Middle East energy coverage for procurement, standards and project news.
- Explore the solar energy desk for equipment and performance reporting.
- Subscribe to The Energy Edit — free, independent reporting, start here.
Exporting equipment into Gulf renewable projects? Explore partnership with Arcnex Energy.
ANSWERS
Questions answered in this story
What is SABER?
SABER is Saudi Arabia's electronic conformity assessment platform, operated under the SALEEM product safety programme. Importers and suppliers register products and shipments through it to obtain the certificates required for market access and customs clearance.
What is the difference between a PCoC and an SCoC?
A Product Certificate of Conformity is issued against a product model to confirm it meets the applicable SASO requirements, and is typically valid for one year. A Shipment Certificate of Conformity is issued for each consignment entering the Kingdom and is what customs requires to release the goods. You generally need the PCoC in place before an SCoC can be issued.
Do solar panels and inverters fall under SASO technical regulations?
Yes. SASO has implemented technical regulations covering small-scale solar PV systems, applying to solar panels, inverters, assembly boxes and related components, with requirements spanning electrical safety, fire safety and electromagnetic compatibility.
Does an IEC test report from my home market count?
It can help, since PV has been brought within the SASO IECEE recognition arrangements, but recognition is not automatic and the accepted scheme and scope change over time. Confirm with your conformity assessment body which of your existing reports are usable before assuming they transfer.
Does a conformity certificate mean I can connect the equipment to the grid?
No. Product conformity and network connection approval are different processes run by different bodies. An inverter can be compliant as an imported product and still not be approved by the relevant network operator for connection.